Measure net slab area
Calculate the slab footprint from drawings or field measurements and split irregular slabs into simple shapes.
Deduct only openings that truly displace concrete; small penetrations may be handled differently by project practice.
Apply the specified thickness
Volume = area × thickness in consistent units.
A 4 in slab uses 4 ÷ 12 = 0.333 ft for the volume calculation.
Convert to cubic yards
Cubic yards = cubic feet ÷ 27.
Keep geometric volume separate from any allowance for subgrade variation, spillage, form deflection, or finishing needs.
Order on the correct basis
Ready-mixed concrete is supplied by fresh concrete volume, while bagged concrete uses product-specific package yield.
Confirm minimum-load, delivery, placement, and project specification requirements before ordering.